A client needed a painting rollout completed on 90 locations in 30 days.
Scope
The scope of work needed to execute the project included:
- Paint 90 gas stations across two states.
- Work needs to be completed in 30 days and needs to start the 1st of the month.
- Each location has a list of certain items to be completed with a priority level of order associated with each.
- Each store has a pre-determined budget.
- If for any reason cost may exceed the pre-determined budget, the client must be contacted to review and approve the new costs.
- Specific client approved paint and color scheme must be followed.
- Supply the client with detailed updates including photos to ensure compliance.
Challenges
The constraints of the project include:
- Organizing and scheduling crews for 90 stores in the 30 day timeframe.
- Ordering the proper materials within a 3 day turnaround.
- Educating all crews on the scope of work and properly equipping all crews with correct paints.
- Weather contingency plans must be determined.
Solution
When a project has such a restrictive time schedule, thorough planning is crucial. The tendency to immediately jump into execution can actually be a project’s downfall. Instead, by having a calculated outline and specific plans to deal with inclement weather, we were able to complete the entire painting project within the specified timeframe.
Our solution to this project included:
- All projects are entered on a master calendar so that the appropriate crew members and supervisors can be dispatched.
- Suppliers are contacted to order the necessary paint specs.
- Time is set aside for all crew members to educate and brief the team on the scope of work and to explain the procedures for paperwork and updates to client.
- Back up crews are organized and put on stand-by in the event of inclement weather.
- Crews are in constant communication with an office based contact so that budget is tracked. If a particular store is nearing the “do not exceed amount” the Home Office support contacts the client to explain the necessary cost.
- Each crew is provided a digital camera in supply the client with updates and a visual progress report.
Summary
Resicom is a thinking company that is committed to developing effective project planning before beginning a single step of execution. By taking time to formulate our strategy and creating contingency plans, Resicom can guarantee a project’s overall success, an also minimize wasteful and excess spending.